A City of Dallas Chapter 380 grant pays against proof, not promises: each payment turns on records showing you hit the jobs, wages, investment, and timeline the agreement names. Here is which facts you must prove, where each number actually lives, and where software helps versus where a person has to sign.

In this guide

If your Dallas-Fort Worth company signed — or is about to sign — a City of Dallas Chapter 380 grant, the agreement does not pay you for showing up. It pays against proof. Each disbursement, and whether any of it is clawed back, turns on records that show you hit the jobs, wages, investment, and timeline the agreement names. So the real work starts the day you sign: standing up the evidence that will clear each payment, pulled from the systems that already hold the numbers, with a person who owns what gets certified.

What a Chapter 380 grant actually pays for

A Chapter 380 grant is public money a Texas city gives a business to cause investment that would not happen the same way without the incentive. Dallas makes these grants under Chapter 380 of the Texas Local Government Code, and its Economic Development Incentive Policy — adopted in 2023 and amended most recently on January 28, 2026 — states that payment or abatement is contingent upon compliance with the incentive agreement throughout the term. Two things follow. First, a “but for” rule: any jobs created or investments made before the agreement is executed do not count toward the minimum requirements. Second, eligibility is conditional and ongoing — an applicant must supply a Texas Comptroller certificate of account status showing it is current on state taxes, and the City can turn down a company that previously defaulted on a Dallas incentive agreement. The grant is a promise to pay if you perform and keep performing, not a check at closing.

The four things a Chapter 380 grant makes you prove

Most Dallas Chapter 380 agreements rest on four measurable promises: a job count, a wage floor, a capital investment, and a deadline. A real, public agreement shows the shape. In a 2025 City of Dallas conditional grant agreement, Dallas Metal Fabricators & Maintenance agreed to create, retain, or relocate at least 40 grant-eligible jobs, meet a minimum salary requirement of $22.06, and put $750,000 of improvements into the property by December 31, 2026, in exchange for a grant not to exceed $100,000. That is one public example, since superseded by a later agreement; yours will use different numbers, but almost always the same four levers. Each is a figure someone has to produce, on a schedule, from a source the City will accept.

See how Clairvance assesses and builds a compliance-evidence workflow in a first AI implementation.

Where each number actually lives

The reason these reports hurt is that no single system holds all four numbers, and the person who owns each system is usually not the person who signs the report. The map below is an operating method — not legal advice and not a promise that following it keeps any grant — for assigning each promise to its authoritative source, its owner, and the artifact that proves it.

PromiseWhat actually countsAuthoritative sourceOwnerEvidence artifactVerification check
Jobs created, retained, or relocatedGrant-eligible positions at the covered location, as the agreement defines them — not every hireHRIS and payroll, filtered by work locationHRPeriod headcount roster tied to payroll for the siteReconcile the roster to payroll; confirm each counted job meets the location and employment-status test
Wage floorThe agreement's minimum salary or wage for the counted jobsPayrollFinance and HRWage report listing each counted job against the floorRecompute against the exact floor written in the agreement, not a city or market average
Capital investmentQualified improvements at the property, incurred after the agreement is executedFixed-asset ledger and accounts payableFinanceInvoice-level capital schedule mapped to the property and datedTie each dollar to an invoice; confirm the date passes the but-for rule
Timeline and completionThe milestone the agreement sets, often a certificate of occupancy or the building openingProject and permitting recordsProject leadCertificate of occupancy and dated completion evidenceConfirm the artifact's date falls on or before the deadline

The counting traps that cause a miss

Most misses do not come from falling short of the target; they come from counting it wrong. Four traps recur. Headcount: staffing-agency or contract workers may not be grant-eligible jobs, and the agreement, not your org chart, decides. Location: a position filled at the right wage but based outside the covered site often does not count. Capital: an invoice booked before the agreement was executed fails the but-for rule even if the money was clearly spent on the project. Timeline: a completion artifact dated a day after the deadline is a miss, however finished the building is. Each trap is a definition question, and the definition is in your agreement, not in a generic jobs or capex report. Build the filters that answer those definitions into the data pull, so the report counts what the agreement counts.

What recapture actually costs

Recapture is agreement-specific, so read yours before you panic or relax. Some Dallas agreements limit the City's remedy to money not yet paid: in the Dallas Metal Fabricators agreement, on termination the grantee simply has no further right to the unpaid grant — you forfeit what you have not yet earned, not what you were already paid. Others tie recapture to a specific installment, or secure performance with instruments the City can call. Dallas's policy lists the security it may require: a promissory note, deed of trust, surety bond, letter of credit, or third-party guarantee. Knowing which remedy your agreement uses tells you how costly a single missed milestone is — and therefore how much evidence rigor each promise deserves.

The public record is watching too

Your agreement is not private. Texas requires the City to report every Chapter 380 agreement it enters, amends, or renews to the Comptroller's eSystems database within 14 days, and to post a link on the City's own website; failing to do so could carry a $1,000 penalty. So the terms you promised are public and searchable. The practical lesson: the numbers you certify to the City should match what you would say anywhere else — to your board, your auditor, or a reporter reading the database — because the agreement itself already is public.

What to automate, and what a person signs

Automate the assembly; keep the judgment. Pulling a period headcount roster and payroll register, tagging qualified capital in the fixed-asset ledger, and gathering the completion artifacts into one dated package are repetitive and safe to automate — the system is collecting and formatting, not deciding. What stays with a person is every definition call (which jobs and dollars qualify), the reconciliation of the draft against its sources, and the certification itself. A controller's signature on a compliance report is an attestation, and a model cannot own it. This is the same exception-and-review discipline finance teams apply to any close: a good sign the process works is that the time to assemble a report falls, the list of exceptions is explicit, and the certified numbers do not drift from the draft the system produced.

Quick answers

Is a Chapter 380 grant guaranteed once it is approved?

No. Dallas's Incentive Policy makes payment or abatement contingent on compliance with the agreement throughout its term. You earn each payment by proving performance, so an approved grant is a conditional promise, not a sum already yours.

Do jobs or spending before we sign count toward the minimums?

Generally no. The policy's but-for rule excludes jobs created or investments made before the agreement is executed from the minimum requirements, because the incentive is meant to cause activity that would not otherwise happen on the same terms.

What happens if we miss one target?

It depends on your agreement. Some Dallas agreements only forfeit grant funds not yet paid; others tie recapture to a specific installment or to security the City can call, such as a deed of trust or letter of credit. Read the recapture and default sections before assuming the worst or the best.

Who reports the agreement to the state, and does that create work for us?

The City does — within 14 days of entering, amending, or renewing the agreement, into the Texas Comptroller's database. Your job is not to file that record but to keep your own performance numbers consistent with the public terms it shows.

Sources

  • City of Dallas Economic Development Incentive Policy (adopted 2023; amended through January 28, 2026), on compliance-contingent payment, the but-for rule, eligibility, and security instruments: dallasecodev.org, Incentive Policy Document
  • City of Dallas Chapter 380 conditional grant agreement with Dallas Metal Fabricators & Maintenance (jobs, wage floor, investment, deadline, grant cap, recapture of unpaid funds): The Abatement Register, agreement 0011620
  • Texas Comptroller of Public Accounts, reporting Chapter 380 and 381 economic development agreements (eSystems database, 14-day window, $1,000 penalty): comptroller.texas.gov, report an agreement

How we research and review these guides

AI transformation with Clairvance

Put the ideas to work in your business.

We provide AI consulting and implementation for finance operations teams. Bring us the process that is slowing your team down and the systems involved. We can assess the problem with you and discuss a practical implementation.

Discuss your project →

Still exploring? Explore the Workflow Opportunity Workbook →